TOTAL GENERATION CAPACITY AT PRESENT: 21,629 MW(SEPT-2019)
1ST ELECTRICITY USED IN BD: AHSAN MANZIL ,1901
ELECTRICITY ACT FOLLOWED: 2018
HIGHEST GENERATED ELECTRICITY:12,893MW(29-5-2019)
ELECTRICITY IMPORTED FROM INDIA: 1197MW(2*500+197)
QUICK RENTAL PP: 1890MW
BIGGEST SOLAR POWER PLANT: 28MW, HNILA OF TEKNAF
TOTAL DISTRIBUTION LINE: 4,89,000CKT KM
TRANSMISSION LINE: 11,650CKT KM
TOTAL POWER PLANT: 145+
GRID SUBSTATION: 131
CONDUCTOR USED IN TRANSMISSION LINE: ACSR WITH OPTICAL FIBRE
SYSTEM LOSS: 11.96%
DISTRIBUTION LOSS: 9.60%
MAIN SOURCE OF FUEL: GAS(66%)
BIGGEST POWER PLANT: APSCL(1876MW)
HEART OF SUBSTATION: DC BACKUP
1ST HVDC SUBSTATION: VERAMARA
2ND HVDC SUBSTATION: DEBPUR,
COMILLA (500MW)
RAMPAL COAL PP: 1320 MW
MATARBARI ULTRA SUPER CRITICAL PP: 1200 MW
PAYRA THERMAL PP: 1320MW
COAL FIRED PP: BARAPUKURIA PP(525MW)
1ST NUCLEAR PP: RUPPUR NPP(2*1200MW)
2ND NPP: BARISAL (yet TO BE CONFIRMED)
400KV TRANSMISSION LINE: VERAMARA-INDIA
LARGEST TRANSMISSION LINE: KHULNA -VERAMARA(353CKT KM)
UNDER CONSTRUCTION LONGEST TRANSMISSION LINE: 700CKT KM(
MOHESHKHALI- VULTA)
UNDER CONSTRUCTION 765KV TRANSMISSION LINE:
MATARBARI (COX'S
BAZAR)- VULTA (DHAKA)
BORONAGAR (INDIA)- PARBATIPUR
1ST ISOLATED GRID: HATIYA, NOAKHALI
NLDC SITUATED IN: AFTABNAGAR, RAMPURA, DHAKA
PER CAPITA ELECTRICITY CONSUMPTION: 510 KWh
HYDRO POWER PLANT: KAPTAI HYDRO POWER PLANT(230MW)
WASTE MANAGEMENT POWER PLANT: N.GANJ (3MW)
TOTAL UNIT RUNNING COUNTRYWIDE: 143+
UPCOMING HYDRO PP: SANGU RIVER(140MW), MATAMUHURI RIVER
(75MW)
COUNTRY 1ST WIND POWER PLANT: SONAGAJI, FENI
100% POWER COVERAGE AREA: 340UPZILLA
COUNTRY 2ND WIND POWER PLANT: KUTUBDIYA, COX'S BAZAR
WASTE TO ENERGY TREATMENT PLANT: JALKURI, NARAYANGANJ (3MW)
FUEL SUPPLIER IN RNPP: TVEL FUEL COMPANY (RUSSIA)
PALLI BIDDUT SAMITI(PBS): 80
POWER HUB: ASUGANJ, SIDDHIRGANJ, PAYRA, SIRAJGANJ, MATARBARI,
MODUNA.
LARGEST POWER HUB: MOHESHKHALI, 15 POWER PLANT IN A ZONE
HIGH GENERATION , LOW DEMAND AREA: SYHLET
LOW GENERATION HUGH DEMAND AREA: RANGPUR
NOTABLE GENERATION COMPANY:
EGCB, RPCL ,BPDB , APSCL ,BCMCL, KPCL,NWPGCL,WZPDCL, SUMMIT
POWER, ORION,UNITED GROUP, SINHA GROUP etc.
TRANSMISSION COMPANY: PGCB
DISTRIBUTION COMPANY: DPDC,DESCO,PDB, NWPGCL,WZPDCL
FUEL TYPE: GAS, COAL, WIND, SOLAR, WASTE MANAGEMENT, HYDRO,
HFO, HSD, LFO, OIL etc.
VOLTAGE LEVEL IN BD: 11-18KV, 33KV, 132KV, 220KV, 400KV.
COMMUNICATION MEDIUM SUBSTATION to SUBSTATION: SCADA,PLCC
PER UNIT COST OF ELECTRICITY BY FUEL:
hydro- 1.32tk
gas: 2.8tk
coal: 7.38tk
furnace oil : 11.48tk
diesel: 19.30tk
solar: 16.14tk
power imported from india: 5.94tk
MATARBARI PP PRODUCTION COST: 13TK/UNIT
ELECTRICITY COVERAGE: 93%
RENEWABLE POWER |
CURRENT SITUATION |
2041 PLAN |