TOTAL GENERATION CAPACITY AT PRESENT: 20,854MW
1ST ELECTRICITY USED IN BD: AHSAN MANJIL ,1901
ELECTRICITY ACT FOLLOWED: 2018
HIGHEST GENERATED ELECTRICITY: 11,623MW(19sep,2018)
ELECTRICITY IMPORTED FROM INDIA: 1160MW(2*500+160)
QUICK RENTAL PP: 1890MW
BIGGEST SOLAR POWER PLANT: 28MW , HNILA OF TEKNAF
TOTAL DISTRIBUTION LINE: 4,89,000CKT KM
TRANSMISSION LINE: 11,396CKT KM
TOTAL POWER PLANT: 137+
GRID SUBSTATION: 131
SYSTEM LOSS: 11.87%
DISTRIBUTION LOSS: 9.60%
MAIN SOURCE OF FUEL: GAS(66%)
BIGGEST POWER PLANT: APSCL(1876MW)
RAMPAL COAL PP: 1320 MW
MATARBARI ULTRA SUPER CRITICAL PP: 1200 MW
PAYRA THERMAL PP: 1320MW
COAL FIRED PP: BARAPUKURIA PP(525MW)
1ST NUCLEAR PP: RUPPUR NPP(2*1200MW)
2ND NPP: BARISAL (yet TO BE CONFIRMED)
400KV TRANSMISSION LINE: VERAMARA-INDIA
PER CAPITA ELECTRICITY CONSUMPTION: 464KWh
HYDROPOWER PLANT: KAPTAI HYDRO POWER PLANT(230MW)
WASTE MANAGEMENT POWER PLANT: N.GANJ (3MW)
TOTAL UNIT RUNNING COUNTRYWIDE: 143+
PALLI BIDDUT SAMITI(PBS): 80
POWER HUB: ASUGANJ, SIDDHIRGANJ, PAYRA, SIRAJGANJ, MATARBARI, MODUNA.
NOTABLE GENERATION COMPANY:
EGCB, RPCL ,BPDB , APSCL ,BCMCL, KPCL,NWPGCL,WZPDCL, SUMMIT POWER, ORION,UNITED GROUP, SINHA GROUP etc.
TRANSMISSION COMPANY: PGCB
DISTRIBUTION COMPANY: DPDC,DESCO,PDB, NWPGCL,WZPDCL
FUEL TYPE: GAS, COAL, WIND, SOLAR, WASTE MANAGEMENT, HYDRO, HFO, HSD, LFO, OIL etc.
VOLTAGE LEVEL IN BD: 11-18KV, 33KV, 132KV, 220KV, 400KV.
COMMUNICATION MEDIUM SUBSTATION to SUBSTATION: SCADA,PLCC
PER UNIT COST OF ELECTRICITY BY FUEL:
hydro- 1.32tk
gas: 2.8tk
coal: 7.38tk
furnace oil : 11.48tk
diesel: 19.30tk
solar: 16.14tk
power imported from india: 5.94tk
ELECTRICITY COVERAGE: 95%